43
ER EC T I N G
7.4
Frame and enclosure
7.4.1
EMC measures for enclosure
7.4.1.1 EMC seals between sections
EMC seals must be provided between two UPS sections. Frame connections must be provided in 225 mm dis-tance.
EMC sealing must be provided between two MNS-Up sections as well as between MNS-Up sections and other MNS sections.
7.4.1.2 EMC seals for roof plates
Roof and bottom plates need to be fixed with all screw holes which are provided in 225mm distance. No addi-tional EMC
sealing is required.
7.4.1.3 EMC seals for bottom plate
All MNS-Up sections require bottom plates due to EMC requirements. The bottom plates need to be fixed in a distance
of 225 mm, and no additional EMC seals are required.
7.4.2
EMC seals for shipping splits
UPS sections shall be joined with partition wall 19 between two MNS-Up sections, as well as between MNS-Up section and
MNS sections. EMC sealing needs to be provided on both sides of the partition wall 19, at top and bottom.
7.4.3
Rear walls and side walls
Rear walls and side walls are unpainted on the inside surfaces where they touch the section frame.
Rear walls and side walls need to be screwed in a distance of 225 mm to the section frame. Required fixing holes are pro-
vided. EMC sealing shall be added at the top and bottom of the rear walls and side walls.
Figure 7-04 EMC sealing for rear walls of the MNS-Up section
Figure 7-05 EMC sealing for side walls and partition wall 19
EMC sealing
EMC sealing
for side walls
and partition
wall 19
Summary of Contents for MNS-Up
Page 6: ... 01 Introduction ...
Page 8: ... 02 Safety first ...
Page 12: ... 03 General technical data ...
Page 16: ... 04 System description ...
Page 18: ... 05 Packing storage and transportation ...
Page 36: ... 06 Transport ...
Page 40: ... 07 Erecting ...
Page 47: ...47 ERECTING ...
Page 48: ... 08 MNS Up configuration ...
Page 52: ... 09 MNS Up Module installation ...
Page 55: ...55 MNS UP MODULE INSTALL ATION ...
Page 56: ... 10 Handling of EMC boards ...
Page 59: ...59 HANDLING OF EMC BOARDS ...
Page 60: ... 11 Communication boards ...
Page 62: ... 12 MNS 3 0 sections ...
Page 64: ... 13 Commissioning ...
Page 66: ... 14 Operating of MNS Up system ...
Page 68: ... 15 Tightening torques for screw connection in MNS Up ...
Page 72: ... 16 Spare parts ...
Page 74: ... 17 Onsite inspection and maintenance ...
Page 76: ... 18 Maintenance intervals ...
Page 81: ...81 MAINTENANCE INTERVALS ...
Page 83: ......