38
M N S - U P
SER V I C E M A N UA L
6.1.3
Crane transport
For transport by crane, the shipping units are equipped with lifting angles.
Fastening of any lifting device directly to the frame sections is not permitted.
The lifting rope angle at the crane hook must not be larger than 120°. The lifting angles may be removed after the switchgear
has been erected.
The fastening holes for the lifting angles are to be plugged with plugs GMN 775 502 P18, if removing the lifting angles.
6.1.3.1 Guide values for permissible rope loading
Permissible Ioad for a four-rope arrangement, rope angle at crane hook 120°
Rope diam.
mm
Hamp ropes
DlN 83325
kg
Perlon ropes
DlN 83330
kg
Steel ropes
DlN 15060
(160 kg/mm
2
)
kg
8
–
–
890
10
180
400
1440
12
280
600
2100
14
350
820
2900
16
470
1060
–
18
580
1340
–
20
720
1660
–
24
1000
2400
–
30
1600
–
–
36
2400
–
–
For a rope angle of 90°, the permissible load is approximately 40% larger than the values given in the table.
Shipping units with one or two sections are equipped with single angles.
Shipping units consisting of three or four sections are equipped with dual angles
The sign advertising the tilting danger must not be removed before all sections have been secured to the
foundation. Do not put the switchgear down on one edge, because of the danger of considerable mechanical
!
damage.
≤
120°
Figure 6-02 Crane transport, transport unit unpacked
Figure 6-03
Arrangement of lifting angles (plan view of mns-sections)
Summary of Contents for MNS-Up
Page 6: ... 01 Introduction ...
Page 8: ... 02 Safety first ...
Page 12: ... 03 General technical data ...
Page 16: ... 04 System description ...
Page 18: ... 05 Packing storage and transportation ...
Page 36: ... 06 Transport ...
Page 40: ... 07 Erecting ...
Page 47: ...47 ERECTING ...
Page 48: ... 08 MNS Up configuration ...
Page 52: ... 09 MNS Up Module installation ...
Page 55: ...55 MNS UP MODULE INSTALL ATION ...
Page 56: ... 10 Handling of EMC boards ...
Page 59: ...59 HANDLING OF EMC BOARDS ...
Page 60: ... 11 Communication boards ...
Page 62: ... 12 MNS 3 0 sections ...
Page 64: ... 13 Commissioning ...
Page 66: ... 14 Operating of MNS Up system ...
Page 68: ... 15 Tightening torques for screw connection in MNS Up ...
Page 72: ... 16 Spare parts ...
Page 74: ... 17 Onsite inspection and maintenance ...
Page 76: ... 18 Maintenance intervals ...
Page 81: ...81 MAINTENANCE INTERVALS ...
Page 83: ......