![ABB HVC-C 100-150 kW Installation Manual Download Page 36](http://html.mh-extra.com/html/abb/hvc-c-100-150-kw/hvc-c-100-150-kw_installation-manual_2837984036.webp)
5
Installation
5.1
General installation procedure
Preliminary requirements
1.
All required permits to
agree with the local rules,
are granted.
•
There is no voltage on the
AC input cable during the
complete installation
procedure.
Procedure
1. Prepare the site. Refer to section
2. Install the power cabinet. Refer to section
.
3. Install the power supply box. Refer to section
4. Install the control box. Refer to section
.
5. Prepare for commissioning. Refer to section
17.1
.
5.2
Install the power cabinet - general procedure
Preliminary requirements
1.
The site is prepared.
Procedure
1. Prepare the foundation for the power cabinet. Refer to section
2. Unpack the power cabinet. Refer to section
3. Do the mechanical installation of the power cabinet. Refer to section
4. Do the electrical installation of the power cabinet. Refer to section
.
5.3
Install the power suply box - general procedure
Preliminary requirements
1.
The site is prepared.
Procedure
1. Unpack the power supply box. Refer to section
2. Do the mechanical installation of the power supply box. Refer to section
3. Do the electrical installation of the power supply box. Refer to section
Installation
36
6AGA000007-0603-EN | 001