Procedure
1. Strip the insulation from the end of
the cable (A).
2. Prepare the wires:
a. Twist the shield mesh (B).
b. Strip the insulation from the
end of the wires (C) to (F). For
specification, refer to section
c. Crimp ferrules on the end of the
wires and the twisted shield.
3. Loosen the screws on the terminals
(G) to ( K).
4. Connect these wires:
a. Shield (B) to the terminal X1-15
(G)
b. PS1_OK/14 (C) to the terminal X1-12 (H)
c. PS1_OK/13 (D) to the terminal X1-11 (I)
d. OVP_AC_11 (E) to the terminal X1-14 (J)
e. OVP_AC_14 (F) to the terminal X1-13 (K)
5. Tighten the screws to the correct torque. For the specification, refer to section
B
J
H
G
I
K
F
E
D
C
A
Electrical installation of the power supply box
62
6AGA000007-0611-EN | 001