![ABB HVC-C 100-150 kW Installation Manual Download Page 35](http://html.mh-extra.com/html/abb/hvc-c-100-150-kw/hvc-c-100-150-kw_installation-manual_2837984035.webp)
Procedure
1. Install the swivel eye bolts or bolts
with lifting loops (A).
2. Connect the cables (B) of the hoisting
equipment to the swivel eye bolts or
bolts with lifting loops.
3. Move the cabinet to the correct
location.
4.2.3
Move the cabinet with a forklift truck
Preliminary requirements
1.
The cabinet is unpacked.
Refer to section
.
•
Forklift truck. Refer to
Note:
Risk of pinching or crushing, the cabinet is heavy
•
Make sure that the forklift truck can lift the cabinet safely. Obey the
safety instructions that apply to the forklift truck. Take into account
the mass, the dimensions and the center of gravity of the EVSE. Refer
.
Caution:
•
Do not drop the cabinet.
•
Do not tilt the cabinet more than allowed. Refer to section
.
Procedure
1. Move the forks (A) of the forklift truck
in the gaps at the side of the cabinet.
2. Move the cabinet to the correct
location.
A
B
A
Transport
6AGA000007-0603-EN | 001
35