![ABB HVC-C 100-150 kW Installation Manual Download Page 47](http://html.mh-extra.com/html/abb/hvc-c-100-150-kw/hvc-c-100-150-kw_installation-manual_2837984047.webp)
Procedure
1. Move the sliding plates (B) on the
guidance plate to close the cable
inlets and hold the cables (C) in place.
2. Tighten the fasteners (A) to the
correct torque. For the specification,
refer to section
9.6
Install the plates on the foundation
9.6.1
Install the cover plates (metal foundation)
Preliminary requirements
1.
The cabinet is installed on
the foundation.
•
Eight Torx fasteners M5
•
Torx screwdriver
Procedure
1. Install the cover plates (A) and (B).
2. Install the fasteners (C).
3. Tighten the fasteners to the correct
torque. For the specification, refer to
section
9.6.2
Install the front cover plate (concrete foundation)
Preliminary requirements
1.
The cabinet is installed on
the foundation.
•
Four fasteners M10
A
C
B
B
A
C
Mechanical installation of the power cabinet
6AGA000007-0611-EN | 001