![ABB HVC-C 100-150 kW Installation Manual Download Page 58](http://html.mh-extra.com/html/abb/hvc-c-100-150-kw/hvc-c-100-150-kw_installation-manual_2837984058.webp)
14
Electrical installation of the power supply
box
14.1
Electrical installation of the power supply box - general
procedure
Preliminary requirements
1.
The power supply box is
installed on the wall.
•
Procedure
1. Open the door of the power supply box. Refer to section
.
2. Insert the cables to the power supply box through the cable glands. Refer to
section
3. Connect these cables:
a. PE cables to the power supply box. Refer to section
.
b. Auxiliary AC input cable to the power supply box. Refer to section
.
c. Power supply feedback cable to the power supply box. Refer to section
d. Auxiliary DC power cables to the power supply. Refer to section
.
4. Close the door of the power supply box. Refer to section
14.2
Insert the cables to the power supply box
Preliminary requirements
•
Torque wrench
•
•
Auxiliary AC input cable.
.
•
PE cables. Refer to section
•
DC auxiliary power cable.
•
Power supply feedback
cable. Refer to section
.
Electrical installation of the power supply box
58
6AGA000007-0611-EN | 001