7-4 (6)
2UEA001270 Rev. F
ACS2000 User manual
Chapter 7 - Commissioning
MV switchgear
Motor
Insulation tests
1
Type of MV switchgear selected and wired per ABB MV switchgear specification
2
MV switchgear ready to be tested with drive
3
MV switchgear protection relay settings tested
4
Safety devices (door locks, Kirk
®
key, grounding switch, etc.) tested and in operation
5
MCB IS EXCLUSIVELY CONTROLLED BY THE ABB DRIVE
1
Motor installed, aligned and alignment protocol available
2
Motor not coupled to driven load
3
Ground connection completed
4
Motor auxiliaries (bearing lubrication, heater cooling, etc.) ready
1
All power cables to input transformer, between input transformer and drive, and from
drive to motor are meggered, and measured values are within the required limits
2
Test report of the megger test available
Note: If the test is carried out by the commissioning engineer of the drive, an additional
day per drive motor combination needs to be reserved. The test must comply with the
specification.
Summary of Contents for ACS2000 DFE
Page 1: ...Medium Voltage Drives User Manual ACS2000 4 kV ...
Page 2: ......
Page 12: ...LOF 4 4 2UEA001270 Rev F ACS2000 User manual ...
Page 14: ...LOT 2 2 2UEA001270 Rev F ACS2000 User manual ...
Page 40: ...1 12 12 2UEA001270 Rev F ACS2000 User manual Chapter 1 Safety ...
Page 68: ...2 28 28 2UEA001270 Rev F ACS2000 User manual Chapter 2 Power electronics and cabinet features ...
Page 94: ...3 26 26 2UEA001270 Rev F ACS2000 User manual Chapter 3 Control system ...
Page 116: ...5 14 14 2UEA001270 Rev F ACS2000 User manual Chapter 5 Mechanical installation ...
Page 134: ...7 2 6 2UEA001270 Rev F ACS2000 User manual Chapter 7 Commissioning ...
Page 138: ...7 6 6 2UEA001270 Rev F ACS2000 User manual Chapter 7 Commissioning ...
Page 156: ...8 18 18 2UEA001270 Rev F ACS2000 User manual Chapter 8 Local operation ...
Page 213: ......