7.5
Power cables, ground cables and equipotential
bonding conductor
7.5.1
Preparing the cable entry and the cables
NOTICE
7.5.1.1
Maximum number of cables per phase
The maximum number of cables that can be used per phase depends on the type of the drive
and its nominal voltage.
Table 7-1: Maximum number of cables per phase
7.5.1.2
Determining the cable length
1. Determine the required length of a cable between the point of entry and the connection
point inside the cabinet.
2. Cut the cable to the required length before connection.
See layout drawing in “Appendix C – Mechanical drawings” for information on:
- Project-specific cable entry
- Distance between point of cable entry and terminals
- Busbar and fastening hole dimensions
- Busbar designations
See “Appendix D – Wiring diagrams” for information on:
- Conventions for cross-reference and device identification
Risk of damage or malfunction!
- Waste inside the cabinet can cause damage or malfunction.
- If possible, do not cut cables inside the terminal compartment.
- Retrieve any waste which accidentally dropped into the cabinet.
ACS1000 type
2.3 kV nominal voltage
3.3 kV nominal voltage
4.0 kV nominal voltage
A1
1 cable per phase
1 cable per phase
1 cable per phase
A2
2 cables per phase
1 cable per phase
1 cable per phase
A3
2 cables per phase
2 cables per phase
1 cable per phase
Summary of Contents for ACS 1013-A1
Page 1: ... MEDIUM VOLTAGE AC DRIVES ACS1000 air cooled User manual ...
Page 3: ...Contents ACS1000 air cooled User manual ...
Page 5: ... 01 About this manual 01 3 14 ...
Page 16: ......
Page 17: ... 02 Important safety information 02 15 26 ...
Page 28: ......
Page 29: ... 03 Power electronics and cabinet features03 27 50 ...
Page 53: ... 04 Control system 04 51 66 ...
Page 68: ......
Page 69: ... 05 Transportation storage and disposal05 67 74 ...
Page 76: ......
Page 77: ... 06 Mechanical installation 06 75 82 ...
Page 84: ......
Page 85: ... 07 Electrical installation07 83 106 ...
Page 108: ......
Page 109: ... 08 Commissioning 08 107 112 ...
Page 115: ... 09 Operation 09 113 126 ...
Page 129: ... 10 CDP control panel 10 127 150 ...
Page 153: ... 11 Preventive and corrective maintenance 11 151 182 ...
Page 185: ......