Commissioning checklist
This checklist is designed to help you prepare the drive and associated equipment
for commissioning.
8.2.1
Mechanical installation checklist
8.2.2
Electrical installation checklist
1.
Drive installed according to the instructions in this user manual
(3BHS213401 E01 Rev H).
□
2.
Drive securely fastened to the floor (if applicable)
□
3.
Redundant fan unit installed (if applicable)
□
4.
Visual inspection:
- No badly affixed or damaged components
- No foreign objects inside cabinet
- No dirt, dust and humidity inside cabinet
□
1.
Types and cross sections of control cables suitable for the signal type and
signal level
□
2.
Types and cross sections of power cables selected according to the instructions
in this user manual (3BHS213401 E01 Rev H).
□
3.
Pulse encoder connected according to the relevant manual (only applicable for
drives with pulse encoder interface)
□
4.
Cable entry prepared according to the instructions in this user manual
(3BHS213401 E01 Rev H).
□
5.
All control cable screens and conductors are connected according to the
instructions of the user manual, appropriately labeled, and the customer-side
connections are completed
□
6.
Equipotential bonding conductor of drive securely connected at both ends
□
7.
Converter transformer and motor cables not connected at both ends (cables
and drive must be insulation resistance tested (Megger test) before connection)
□
Summary of Contents for ACS 1013-A1
Page 1: ... MEDIUM VOLTAGE AC DRIVES ACS1000 air cooled User manual ...
Page 3: ...Contents ACS1000 air cooled User manual ...
Page 5: ... 01 About this manual 01 3 14 ...
Page 16: ......
Page 17: ... 02 Important safety information 02 15 26 ...
Page 28: ......
Page 29: ... 03 Power electronics and cabinet features03 27 50 ...
Page 53: ... 04 Control system 04 51 66 ...
Page 68: ......
Page 69: ... 05 Transportation storage and disposal05 67 74 ...
Page 76: ......
Page 77: ... 06 Mechanical installation 06 75 82 ...
Page 84: ......
Page 85: ... 07 Electrical installation07 83 106 ...
Page 108: ......
Page 109: ... 08 Commissioning 08 107 112 ...
Page 115: ... 09 Operation 09 113 126 ...
Page 129: ... 10 CDP control panel 10 127 150 ...
Page 153: ... 11 Preventive and corrective maintenance 11 151 182 ...
Page 185: ......