WAGO I/O System 750
Commissioning 103
750-8210/040-000 PFC200; G2; 4ETH; XTR
Manual
Version 1.7.0, valid from FW Version 04.01.10(23)
8
Commissioning
Close any ports and services that you do not need!
Unauthorized persons may gain access to your automation system through open
ports.
To reduce the risk of cyber attacks and thus increase cyber security, close all
ports and services not required by your application in the control components
(e.g., port 6626 for WAGO-I/O-
CHECK
and port 11740 for CODESYS V3).
Only open ports and services during commissioning and/or configuration.
8.1
Switching On the Controller
Before switching on the controller ensure that you
•
have properly installed the controller
(see section
“Installation”),
•
have connected all required data cables (see section
“Connections”) to the
corresponding interfaces and have secured the connectors by their
attached locking screws,
•
have connected the electronics and field-side power supply
(see section
“Connections”),
•
have mounted the end module
(see Section
“Installation”),
•
have performed appropriate potential equalization at your machine/system
(see System Description for 750-xxx) and
•
have performed shielding properly (see System Description for 750-xxx).
To switch on both the controller and the connected I/O modules, switch on your
power supply unit.
Starting of the controller is indicated by a brief orange flashing of all LEDs. After a
few seconds the SYS LED will indicate successful boot-up of the controller.
The runtime system CODESYS V3 is started at the same time.
Once the entire system has been successfully started, the SYS and I/O LEDs
light up green.
If there is an executable IEC 61131-3 program stored and running on the
controller, the RUN LED will light up green.
If no executable program is stored on the controller, or the mode selector switch
is set to STOP, this is likewise indicated by the RUN LED (see Section
“Diagnostics”> … > “Fieldbus/System Indication Elements”).