4. Only for commissioning:
Check the connections for possible
leaks. Replace faulty or displaced
seals.
5.
Check the primary circuit pressure.
The pressure should be approx.
2 bar.
Filling and venting the heating water side
A
A
Fill & drain valve
1.
Open any non-return valves installed
on site.
2.
Check the pre-charge pressure of the
expansion vessel (see page 104).
3.
Thoroughly flush the on-site pipe-
work.
4.
Fill the heating circuit via fill & drain
valve
A
with water; during filling,
check the system pressure at the
pressure gauge.
Minimum system pres-
sure
0.8 bar
Permissible operating
pressure
3 bar
5.
Close fill & drain valve
A
.
6.
Open a suitable air vent valve in the
heating circuit.
7.
!
Please note
To prevent equipment dam-
age, check the flow and return
connections of the secondary
heat pump circuit for
leaks
.
In case of leaks, immediately
shut off the equipment, drain
the water and check the seat-
ing of the seal rings. Replace
all seal rings that may have
slipped.
8.
Switch ON the power.
9.
Remove the cause if the phase mon-
itor has responded. The relay does
not need to be reset.
Commissioning, inspection, maintenance
Further details regarding the individual steps
(cont.)
5368 522 UAE
Service
Содержание Vitocal 300-G BW
Страница 57: ...57 6 1 2 4 3 5 A 5x Installation sequence Opening the heat pump 5368 522 UAE Installation...
Страница 188: ...188 VITOCAL 300 205 025 011 203 202 200 206 207 204 201 010 025 A 026 Parts lists Parts lists type BWC cont 5368 522 UAE...
Страница 194: ...194 VITOCAL 300 205 203 202 200 206 207 204 201 010 026 025 A 025 Parts lists Parts lists type BW cont 5368 522 UAE...
Страница 213: ...213 5368 522 UAE...
Страница 214: ...214 5368 522 UAE...
Страница 215: ...215 5368 522 UAE...