To connect two Expansion Shelves to the Primary Shelf
1
Verify that all compute nodes and the Primary Shelf are off and that the power
cords are unplugged.
Do not remove the cables between the compute nodes and the Primary Shelf.
2
Obtain the two SAS-3 cables that ship with each Expansion Shelf.
3
Identify the single SAS-3 port on the left side of each controller module in the
Primary Shelf.
4
Identify ports A and C in each I/O module in the Expansion Shelf. Port B is not
available for use.
5
IMPORTANT: Note the correct orientation of the blue tab on the ends of the
SAS-3 cables. The blue tab must face down in the ports on all shelves.
6
Connect the cables as follows:
■
Connect one cable to each of the SAS-3 ports on the left of each controller
module on the Primary Shelf.
95
Adding Expansion Storage Shelves to an operating appliance that does not have any Expansion shelves
Connecting two Expansion Shelves to the Primary Shelf
Содержание 5350
Страница 1: ...Veritas 5350 Appliance Hardware Installation Guide ...
Страница 13: ...The bottom drawer contains slots 42 through 83 13 Hardware overview 5U84 storage shelf drawers and disk drives ...
Страница 64: ...64 Hardware installation procedures Connecting the hardware to one compute node ...