4. COMMISSIONING
Before commissioning, read the warnings and instructions listed in
Chapter 1!
4.1 Commissioning steps of Vacon 10
1
Read carefully the safety instructions in Chapter 1 and follow them.
2
After the installation, make sure that:
• both the frequency converter and the motor are grounded.
• the mains and motor cables comply with the requirements given in Chap-
ter 3.2.4.
• the control cables are located as far as possible from the power. cables
(see Chapter 3.2.5, step 2) and the shields of the shielded cables are con-
nected to protective earth.
3
Check the quality and quantity of cooling air (Chapter 3.1.2).
4
Check that all Start / Stop switches connected to the I / O terminals are in
Stop
-
position.
5
Connect the frequency converter to mains.
6
Set the parameters of group 1 according to the requirements of your application.
At least the following parameters should be set:
• motor nominal speed (par. 1.3)
• motor nominal current (par. 1.4)
• application type (par. 17.1)
You will find the values needed for the parameters on the motor rating plate.
Содержание 10
Страница 1: ......
Страница 17: ...14 vacon installation Tel 358 0 201 2121 Fax 358 0 201 212205 3 MI1 MI3 3P 230 V POWER LOSS ...
Страница 18: ...installation vacon 15 24 hour support 0 201 212 575 Email vacon vacon com 3 ...
Страница 19: ...16 vacon installation Tel 358 0 201 2121 Fax 358 0 201 212205 3 MI1 MI3 1P 230 V POWER LOSS ...
Страница 20: ...installation vacon 17 24 hour support 0 201 212 575 Email vacon vacon com 3 ...