each side of the machine with a bolt (1/2 x 1-1/2
inches) and a locknut (1/2 inch) as shown in
9.
Torque the bolt and locknut to 91 to 113 N∙m (67
to 83 ft-lb).
10.
Repeat steps
through
at the other side of the
tank skid and machine.
14
Installing the Center Boom
Section
Parts needed for this procedure:
1
Center-boom assembly
10
Bolt (3/8 x 1 inch)
10
Flange locknut (3/8 inch)
2
Boom-transport cradle
4
Bolt (1/2 x 1-1/4 inches)
4
Flange nut (1/2 inch)
Assembling the Boom-Transport
Cradles
1.
Attach lifting equipment to the center boom
section and remove it from the shipping
container.
2.
Align the boom transport cradles to the center
boom section (
).
g028458
Figure 37
1.
Boom-transport cradle
4.
Horizontal hole (boom
center section)
2.
Bolts (3/8 x 1 inch)
5.
Flanged locknut (3/8 inch)
3.
Vertical holes (boom
center section)
3.
Assemble the cradles to the boom section
(
and
) with 6 bolts (3/8 x 1
inch) and 6 flanged locknuts (3/8 inch).
g028459
Figure 38
1.
Locknuts (3/8 inch)
4.
Torque the bolts and nuts to 37 to 45 N∙m (27
to 33 ft-lb).
Installing the Center Boom Section
to the Tank Skid
1.
Start the machine, remove the bed support from
the lift cylinder and stow the support, lower the
tank skid, shutoff the machine, and remove the
key from the starter switch.
2.
Align the bottom hole in the section mounting
brackets of the center boom assembly with the
26