19/126
Siemens Building Technologies
SED2 variable speed drives
CM1U5192en
HVAC Products
Electrical installation
01.2002
4
Electrical installation
The VSD must be grounded.
♦
To ensure safe operation of the equipment, authorized persons must install and
commission it in full compliance with the notes and warnings set out in these
operating instructions.
♦
Take particular note of general and regional installation and safety regulations
regarding work on sites with dangerous voltages (e.g. EN 50178), and of the
relevant regulations for the correct use of tools and personal protective equipment.
♦
The cross-section of the ground bonding conductor must be at least equal to that of
the mains connection cables.
Dangerous voltages may occur at the following terminals even when the
variable speed drive is not running:
-
Power supply terminals L1, L2, L3.
-
Motor terminals U, V, W, DC+, DC-.
-
Link terminals DC-, DC+/B+, DC/R+, B-.
After switching off the supply voltage, wait at least 5 minutes before starting any
installation or service work.
4.1 General
4.1.1
Maximum length of motor cables
The performance data given in the specifications cannot be guaranteed if the motor
cables exceed the following lengths:
50 m for shielded cables
100 m for unshielded cables
For devices featuring EMC filters, the maximum cable length is 25 m. For cables
shorter than > 25 m, the EMC guideline for filtered devices does not apply.
If you connect several motors to one VSD, the individual motor lines must be added to
the total line length.
4.1.2
Operation with ungrounded systems
SED2 variable speed drives with a protection standard of IP20 operate in ungrounded
systems, and remain in operation when an input phase connects to ground. In the
event of an output phase with a ground fault, the SED2 switches off and displays
message F0001.
SED2 drives with a protection standard of IP54/NEMA 12 cannot be operated in
ungrounded systems.
4.1.2.1
Precautions for ungrounded systems (IT protective systems)
In ungrounded systems, remove the Y capacitor, or break the connections to this
capacitor and integrate an output choke. The following procedure shows how to remove
or disconnect the capacitor.
Operation in ungrounded systems is possible only using the SED2, IP20, without
filter.
Danger
Danger
Note
.
.
.
.
IP20/NEMA 0
IP54/NEMA 12
Important
Содержание SED2 Series
Страница 2: ...2 126 Siemens Building Technologies SED2 variable speed drives CM1U5192en HVAC Products 01 2002 ...
Страница 10: ...10 126 Siemens Building Technologies SED2 variable speed drives CM1U5192en HVAC Products Introduction 01 2002 ...
Страница 52: ...52 126 Siemens Building Technologies SED2 variable speed drives CM1U5192en HVAC Products Commissioning 01 2002 ...
Страница 125: ...125 126 Siemens Building Technologies SED2 variable speed drives CM1U5192en Landis Staefa Division Index 01 2002 ...