B.4) Preliminary Operations
Prior to beginning the installation procedure, perform the following controls and
preparatory steps:
A
) P
REPARATION OF THE
P
LACE OF
I
NSTALLATION
•
Check that there is an efficient lighting system in the room.
•
Check that the room and pit are clean.
•
Check that the mains electricity has sufficient grounding (if this is not the case, halt
installation until the Customer has rectified the situation).
•
Check that the shaft entrances are closed suitably.
•
Set up a materials storage area near the shaft that is easily accessible for the
installers and not exposed to the elements.
•
Check that all of the conduits and holes for the electric cables are free, available for
inspection, and well finished.
B
) M
ATERIALS
U
NLOADING AND
S
TORAGE
•
Ensure that the characteristics of the Control Panel (Type of panel, meters, start-
ups ...) correspond to what was ordered and what is listed on the order
confirmation.
•
Check that all of the material needed for installation is available, according to the list
attached to the documents for the panel. The part numbers for the materials are
located on the bags that contain the parts and are called out in the installation
instructions in this manual.
•
Check the status of all components and materials upon receipt on site in order to
identify any possible damages due to transport. Immediately notify SEA SYSTEMS
S.r.l. is there are any missing or damaged parts.
•
Store the electric and electronic components in a dry cool place, in their original
packaging.
•
If, for any reason, immediate installation of the plant is not possible, periodically
check on the stored components to avoid damages caused by extended storage
under unfavorable conditions.
C
) S
CAFFOLDING
•
Use regulation scaffolding for the installation. The scaffolding must have work levels
at each stop, approximately 0.5 m lower than the floor.
CAUTION
Scaffolding made completely or partially from metal must be grounded and
comply with the current safety standards.