B.7) In Shaft Mounting and Connections
B.7.1 S
HAFT
L
INE
(S
HAFT
U
PRIGHT
)
1. The shaft line is made up of a taped coil of colored or numbered wires, with insert connectors
and labeled for the panel side.
2. Fasten the shaft line conduit (p/n P-00060) using the provided plugs (p/n P-00075) near the
floor button panel, keeping it at most 1 m from the door.
If two operators, install the same conduit closest to the side with most services
NOTE
Insert the strap (p/n P-00074) in the plug (p/n P-00075) before fastening the
conduit. (Fig. 1).
3. Fasten the coil temporarily at the top of the shaft and lower it into the shaft from the top,
allowing it to descend along the side with the insert connectors, to the control panel. (Fig. 2)
Fig.
1
Fig.
2
4. Connect the connectors of the upright to the operations panel according to the installation
schematic diagrams.
5. Extend the coil starting from the panel side, fastening it with a few straps to the plugs that hold
the conduit until you reach the very top of the shaft.
CAUTION
If the cable is tool long when it reaches the top, cut the wires and isolate them