9. Remove any installation tools (e.g. the lift bar).
10. Apply anti-seize compound to the system screws and install the screws.
11. Torque the system screws in a cross pattern, gradually increasing the
torque to specified value.
12. Install the screw to secure the electrical and solenoid interface to the
exterior of mold base.
13. Install the clamp plate.
14. Connect all water lines and test. Water temperature is not to exceed 30°C
(85°F).
15. Water to FUSION SERIES
®
G2 valve actuators must be turned on before
heating is activated.
16. Connect all electrical, hydraulic / pneumatic lines, as applicable.
8.4.1 Installation of a System with Flanged Nozzles
1.
Inspect the flanged nozzle and if necessary, clean away any plastic
residue.
2.
Loosen the shoulder bolts on each nozzle flange.
3.
Adjust the flange position to make sure both ball plungers are sitting
completely inside the manifold dimples.
4.
Tighten the shoulder bolts to the specified torque.
5. Follow the system installation instructions called out in General Assembly
drawings to install the system into the cavity plate.
8-4
© 2020 Mold-Masters (2007) Limited. All Rights Reserved.
SYSTEM INSTALLATION
FSG2 User Manual