363-205-401
Power Up: NTP-005
Issue 7, March 1997
Page 3 of 4
DO ITEMS BELOW IN ORDER LISTED
FOR DETAILS, GO TO
4.
NOTE:
One BFU is required for each partially or fully equipped dual
bank assembly in the frame. If adding to an existing RT dual
bank assembly, an additional BFU is not required.
Install and check fuses in BFU (bank fuse unit) in bulk power
shelf, if necessary.
5.
Install (if not previously installed) 3C RINGING GENERATOR in
bulk power shelf.
6.
NOTE:
The AUG1 PRU is required only if multiparty channel units
that require positive ringing current are to be installed in any
of the dual bank assemblies served by the bulk power shelf.
One PRU is required for one or two dual bank assemblies
containing multiparty channel units. A second PRU is
required when the bulk power shelf serves three dual bank
assemblies containing multiparty channel units that require
positive ringing current.
Install (if not previously installed) AUG1 PRU in bulk power shelf
(if required).
7.
Install and test PCU (power converter unit) in facility shelf.
8.
Remove PCU. Repeat previous Step for each new dual channel
bank assembly.
9.
Update records to indicate that RT supporting equipment has
been installed. When required, perform RT Turn Up procedures
for the appropriate Feature Package.