363-205-401
Power Up: NTP-004
Issue 7, March 1997
Page 3 of 4
DO ITEMS BELOW IN ORDER LISTED
FOR DETAILS, GO TO
5.
NOTE:
Batteries must have been on charge for at least 48 hours
before testing with 197A BATTERY LOAD TEST SET. If
batteries have just been put on charge, the remainder of this
procedure may be performed and batteries can be tested at
a later date.
Perform test of RT batteries using 197A BATTERY LOAD TEST
SET.
6.
NOTE:
One battery charger is required per battery string.
Install 337A BATTERY CHARGERs in Frame-type RT, 80-type
CSC (community service cabinet), 90-type cabinet
(ED-7C621-30, ED-97977-30, or ED-7C699-30), or 51-type
(ED-7C601-30) cabinet RT.
7.
If adding AC rectifiers to an existing system, continue with Step 8.
Otherwise, proceed to Step 9.
8.
Install 336A RECTIFIERs in power shelf.
9.
Install (if not previously installed) and check fuses in second BFU
(bank fuse unit) in power shelf.
10. If powering a SLC Series 5 RT dual channel bank, continue with
Step 11. Otherwise, proceed to Step 13.
11. Install and test PCU (power converter unit) in facility shelf.
12. Remove PCU. Repeat previous Step for each new dual channel
bank assembly.
13. Update records to indicate that RT supporting equipment has
been installed. When required, perform RT Turn Up procedures
for the appropriate Feature Package.