Power Up: DLP-512
363-205-401
Page 4 of 4
Issue 7, March 1997
12.
NOTE:
If voltage requirements are not met after replacement battery pack is
installed, original battery pack should be reinstalled in battery shelf.
Replace one battery pack.
13. On battery shelf, connect DMM test leads to +BAT jack (J5) and
−
BAT jack
(J6).
14. Does meter indicate greater than 45.0 volts DC?
If YES, then proceed to Step 18.
If NO, then continue with Step 15.
15. Have all battery packs been replaced?
If YES, then continue with Step 16.
If NO, then proceed to Step 17.
16. Check wiring and connectors on battery shelf. Repeat procedure from Step 8
after locating and correcting trouble.
17.
NOTE:
If voltage requirements are not met after replacement battery pack is
installed, original battery pack should be reinstalled in battery shelf.
Replace another battery pack and repeat from Step 13.
18. Have all equipped battery shelves been tested?
If YES, then proceed to Step 20.
If NO, then continue with Step 19.
19. Go to next battery shelf and repeat from Step 8.
20. Remove DMM. Install good fuses (15-amp) into +BAT and
−
BAT fuse holders
of all battery shelves equipped with batteries.
21. Insert connector J113 into connector P113 on battery shelf.
STOP. YOU HAVE COMPLETED THIS PROCEDURE.