Power Up: NTP-003
363-205-401
Page 4 of 4
Issue 7, March 1997
DO ITEMS BELOW IN ORDER LISTED
FOR DETAILS, GO TO
12.
NOTE:
The AUG1 PRU is required only if multiparty channel units
that require positive ringing current are to be installed in the
dual bank assemblies.
Install AUG1 PRU in power shelf (if required).
13. Install (if not previously installed) and check fuses in BFU (bank
fuse unit) in power shelf.
14. If powering a SLC Series 5 RT dual channel bank, continued with
Step 15. Otherwise, proceed to Step 17.
15. Install and test PCU (power converter unit) in facility shelf.
16. Remove PCU. Repeat previous Step for each new dual channel
bank assembly.
17. Update records to indicate that RT supporting equipment has
been installed. When required, perform RT Turn Up TAB proce-
dures for the appropriate Feature Package.