Installation
53
Due to our policy of continuous product innovation, some specifications may change without notice.
©LG Electronics U.S.A., Inc., Englewood Cliffs, NJ. All rights reserved. “LG” is a registered trademark of LG Corp.
Grid and Load Connections
y
Must use copper or aluminum wire rated at 90 °C (194 °F) for the AC power connection.
y
Strip the ends of the wires and insert into the corresponding SE Box terminal lugs.
y
Using the proper torque tool, tighten the lugs according to the table on the following page.
INFO
a
Connect the grid conductors (L1, L2, Neutral, and Ground) to grid terminals in the SE Box as
shown in the following figure.
When a main breaker is required, install the main breaker ahead of wiring connection. Please
refer to "SE Box Main Breaker Installation". (Follow the local code.)
L1 (Black)
L2 (Red)
N (White)
G (Green)
From Grid
5/6 inch Hex
317 kgf·cm (275 lbf·in)
torque
1/4 inch Hex
288 kgf·cm (250 lbf·in)
torque
Flat head screwdriver
2 – 2/0 AWG –
58 kgf·cm (50 lbf·in) torque
6 – 4 AWG –
52 kgf·cm (45 lbf·in) torque
14-8 AWG –
40 kgf·cm (35 lbf·in) torque