HEATING OPTION
e-BALTIC-IOM-2020.12-EN
76
CONDENSATE DRAIN
WARNING: Do not forget to connect the condensate drain (No need to add a siphon). The condensates must absolutely be
drained at least 5 meters from the unit into an appropriate place. The condensates are corrosive and could damage the unit
(or other parts of the installation) if they are not drained properly.
COMMISSIONING
The gas module unit is supplied with settings entered and tested for the gas specified on the nameplate. Before turning on the
gas module in the unit, check the following:
•
Vent the gas supply line and carefully let the remaining air out of the pipes.
•
Restore the gas supply piping after venting and check that there are no leaks, use a soapy solution or equivalent
product, do not use open flames.
•
Check that electrical connections indicated in electrical diagrams attached to the unit
•
Check that efficient earthing connections have been completed, carried out as specified by current safety regulations;
•
Provide power to the heater with the general switch on the machine and insert the power plug in the inside of the
compartment;
•
After the pre-wash time, the ignition spark occurs. After the third failed ignition attempt, the device locks up. After 10
seconds, it is possible to unlock the device by resetting the burner control equipment.
•
After opening the gas solenoid valve, the burner ignites.
•
After the stabilization of the working conditions (about 15 min.), Carry out a combustion analysis and a performance
measurement.
•
Check that the safety thermostat (Tso) switches off the burner.
Condensate drain connection