HEAT RECOVERY
e-BALTIC-IOM-2020.12-EN
45
ENERGY RECOVERY INSTALLATION (ERVF+HRMV) ON UNITS E+ BOX
1.
Install the flowcurb
2.
Before installing the rooftop:
a.
Fix the brackets (5 pieces) on the curb by 24 screws
(6x16mm);
b.
ADJUST the position of the attachment
bracket so that it is 5 mm above the support
surface (without the foam);
c.
Install the foam (25x10 mm) on the upper part of the
flowcurb.
3.
a. Fix the lower mounting bar of the heat
recovery module using 4 screws (6x16 mm)
and remove the side doors;
b. Make sure that the foam is not damaged (20x15 mm).
4.
Install the rooftop and remove the lifting covers
5.
Place the two upper mounting bars through the
two top slots.
6.
Install the heat recovery module on the bracket
by taking care to position properly the lower
mounting bar
Don't forget to remove the lifting covers from the module.
7.
Slide the 'T' plate into the lifting lug and place the bolt through it. On the opposite
side, place also the bolt.
8.
Finally tighten the heat recovery module with the 4 bolts 8x60mm to compress the foam
(2 bolts on the upper mounting bars (detail) and the 2 bolts placed in step 7).
2c
x4
2a
x6
x2
5
mm
2b