![Lake Shore 648 Скачать руководство пользователя страница 40](http://html1.mh-extra.com/html/lake-shore/648/648_user-manual_670640040.webp)
30
CHAPTER 3:
Installation
Model 648 Electromagnet Power Supply
3.11.2 IEEE-488
Interface Connection
An IEEE-488 port has been provided to allow remote computer control of the power
supply. Refer to Chapter 5, Computer Interface Operation.
3.12 Chassis
Connection
A 10-32 screw has been provided for attaching an optional chassis ground
connection. This connection is normally not required. However, occasionally there are
noise problems associated with a floating magnet or other ancillary equipment.
3.12.1 3-Phase Power
Connections
All 3-phase electrical wiring should be completed by a qualified electrician adhering
to all local codes and standards, prior to the arrival of a Lake Shore representative for
installation and training.
The qualified electrician should refer to the Model 648 electromagnet power supply
manual, Chapter 3, to complete the connection of 3-phase power to the Model 648.
If you use a 3-phase water chiller, refer to the Water Chiller manual to complete the
connection of 3-phase power to the water chiller.
3.12.2 Attach the Floor
Mounting Option
This section briefly outlines the steps necessary to install the floor mounting option.
You will need the Model 648 floor mount kit.
Consult with the facilities personnel to confirm that the floor may be modified to support
the floor mounting option and to determine the location of water or gas lines that may be
present.
There are safety issues concerning the installation of the floor mounting option. These
issues can vary depending upon the method and tools you use. These directions are
intended only to give a brief summary of the installation process. Consult local codes and
regulations before installation.
1. Place the power supply in its designated position.
2. Obtain the four anchoring brackets as shown in FIGURE 3-15.
3. Attach the brackets oriented at 90° angles from the power supply base.
4. Use the hole in each of the bracket as a template, and trace their positions on the
floor.
Floor mount
5. Move the power supply away from its designated position to reveal the traced
circles.
6. Using the traced circles as a guide, drill mounting holes in the floor according to
local codes and regulations.
7. Move the power supply back to its designated position.
8. Attach securing hardware to fasten the floor mounting straps to the floor.
FIGURE 3-15