![KW DAVID-613 Скачать руководство пользователя страница 20](http://html1.mh-extra.com/html/kw/david-613/david-613_manual_2013611020.webp)
KW Aufzugstechnik GmbH Inbetriebnahme DAVID-613
DAVID-D613-Inbetriebnahme-V124-EE 18.02.2022 Seite - 20 -
Schematic diagram- reduced pit
Reduced head
Functional Flow – Reduced shaft pit
Pos activity
1
Opening the bottom landing door
Shelter shows
RED
2
Press the emergency brake switch
3
Press the shaft light button
4
Anchoring the pit ladder
5
Erect the service support under the cab
Temporary shelter made
Shelter shows
GREEN
... Further activities according to action plan
Assembly Effort
- Reduced shaft pit
Pos Component / switch
clamp
1
Connecting the door release monitor-
ing S9.1 Milestone door monitoring
9.1 & 9.1
2
Connection of the reset key switch
200 & 68R
3
Mounting the maintenance support for
the cabin
4
Connection NC contact for SiKr.
maintenance support cabin in X6
3L & 3M
5
Connection normally open contact for
SiKr. maintenance support cabin in
X6
4L & 4M
6
Connection normally open contact for
traffic light Maintenance support cabin
in X6-XP
5L & 5M
7
Assembly shelter traffic light pit
8
Connection in shaft box X6-XP
GR-500-GG
Functional flow – Reduced pit brow
Pos activity
1
Opening the bottom landing door
2
Actuation of the emergency brake switch
3
Actuation of the Shaft light switch
4
Anchoring the pit ladder
5
Erecting the maintenance support Counterweight
Temporary shelter cabin made
6
Leaving the pit with reversing the
Measures pit ladder & emergency brake switch
7
Open the corresponding landing door to access the
cabin roof.
Shelter shows
GREEN
8
Actuation of the emergency brake switch
9
Erecting the cabin folding railing
10
Switching on the inspection switch
Inspection operation possible!
Assembly Effort -Reduced pit brow
Pos Component / switch
clamp
1
Connection of door release monitor-
ing S9.2 to S9.n to X1/
X1/ 14 & 15
2
Assembly of maintenance support
Counterweight
3
Connection NC contact for SiKr.
maintenance support cabin to X6
3M & 3N
4
Connection normally open contact
maintenance support cabin to X6
4M & 4N
5
Connection normally open contact
Maintenance support Counterweight
5M & 5N
6
Mounting of shelter traffic light Kabi
sunroof
7
Connection of the traffic light in the
inspection box to X11-SRA
KR-500-KG
8
Folding railing assembly Kabi-ne
9
Connection NC contacts for SiKr.
folding railing 1 & 2 to X11
3F & 3G
3G & 3H
10
Connection of normally open con-
tacts for folding railings 1 & 2 to X11
4F & 4G
4G & 4H