Filling the TANKS with the Developer and Fixer Solutions
981088 – September 1995
67
Section 15: Filling the TANKS with the Developer and Fixer Solutions
Mixing the Chemicals
Warning
Wear rubber gloves, safety glasses, and protective clothing when mixing chemicals and filling the TANKS.
Important
• When mixing chemical solutions, follow all instructions and precautions on the labels of the chemical bottles.
• Mix only a 2-week supply of developer replenisher.
[1] Following all directions provided with the chemicals, mix at least 19 litres (5 gallons) of replenisher.
[2] Before adding fresh chemicals to an empty PROCESSOR, check that the developer and fixer DRAIN VALVES
are fully closed. The DRAIN VALVE KNOBS should be pushed in and rotated
1
⁄
4
turn.
Figure 58
Closing the DRAIN VALVES
H130_0019BA
PANEL
DISPLAY
DRAIN VALVES
H130_0019BCA
FEED TRAY