NO TE
● Components shown by (5) and (6) in the preceding figure are delivered with the smart
cooling product. Other components need to be purchased and installed onsite. Do not
install the other components directly under the cabinet.
● A water filter with 20 meshes and pressure resistance of 1.6 MPa or higher is
recommended onsite. Pressure resistance of the water filter is determined by site
requirements. Install the water filter on the external water inlet pipe near the smart
cooling product.
● Ensure that the effective displacement of the flexible connection is greater than or equal
to 30 mm.
3.1.2 Downflow Layout Requirements
Figure 3-2 System layout diagram
(A) Chilled water inlet
(B) Chilled water outlet
(1) Balance valve or isolation
valve
(2) Water filter
(3) Isolation valve
(4) Flexible connection
(5) Chilled water valve
(6) Heat exchanger
(7) External components
NO TE
● Components shown by (5) and (6) in the preceding figure are delivered with the smart
cooling product. Other components need to be purchased and installed onsite. Do not
install the other components directly under the cabinet.
● A water filter with 20 meshes and pressure resistance of 1.6 MPa or higher is
recommended onsite. Pressure resistance of the water filter is determined by site
requirements. Install the water filter on the external water inlet pipe near the smart
cooling product.
3.1.3 Pipe Layout Requirements
NetCol8000-C(070, 130, 190) In-room Chilled Water
Smart Cooling Product
User Manual
3 Installation
Issue 07 (2021-12-30)
Copyright © Huawei Technologies Co., Ltd.