FusionModule2000 Smart Modular Data Center
Installation Guide
17 Connecting Cables
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
284
Installing Panels
1.
Reinstall the circuit breaker panel.
2.
Secure filler panels to the rack rails on the rear door, as shown in
Each filler panel occupies 2 U. Install them according to the U position markings on the cabinet. Ensure
that filler panels fully cover the rack rails.
Figure 17-23
Installing filler panels
17.8.3 (Optional) Connecting Cables to Industrial Connectors
to
show only the cable connection methods. The industrial
connector cable connections depend on the industrial connector type and wiring port silk
screen.
Figure 17-24
Connecting cables to the industrial connector (three-core cable)