FusionModule2000 Smart Modular Data Center
Installation Guide
14 Installing Power Supply and Distribution Devices
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
176
14
Installing Power Supply and
Distribution Devices
14.1 (Optional) Installing the UPS Outside the Smart
Module
For details, see the document delivered with the equipment or obtain the required document
according to the section "Documentation Preparations."
14.2 (Optional) Installing a Battery Cabinet Outside the
Smart Module
A battery cabinet is installed in the same way as installing other cabinets. The installation
position depends on the bidding design.
14.3 (Optional) Installing Batteries
Precautions
To ensure personal safety, unpack, transport, and install batteries by following the
instructions in the manuals delivered with the batteries.
Except for necessary functional parts, wrap the exposed metal parts of tools such as
Phillips screwdrivers and wrenches with at least two layers of insulation tape.
Wrap the OT terminal of a cable with insulation tape, and remove the tape when the
cable is placed in position and the terminal connection is verified.
Leave one break point disconnected when connecting batteries on each layer, and
connect the break point on each layer after other cables are connected.
Tighten screws to prevent sparks generated upon power-on.
Only qualified technicians can connect battery cables.
Ensure that all the safety measures have been taken before installation.
Ensure that the circuit breakers in the BCB box are OFF during installation.
Never short-circuit the two poles of a battery when handling or installing batteries.