FusionModule2000 Smart Modular Data Center
Installation Guide
15 Installing Monitoring Devices
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
229
Figure 15-70
Installing a smart ETH gateway
Step 2
Connect one end of the ground cable available in the smart ETH gateway package to the
ground point at the lower part of the cable trough using one M4 screw, and connect the other
end to the ground point on the side of the smart ETH gateway, as shown in
The M4 screw used for connecting the ground cable to the cable trough is available in the cable trough
package.
Step 3
Install the smart ETH gateway to the guide rail, as shown in
1.
Align the upper slot of the guide rail for the smart ETH gateway with the upper part of
the guide rail, and pre-mount it onto the guide rail.
2.
Press the lower part of the smart ETH gateway to clamp the smart ETH gateway onto the
guide rail.
3.
Shake the smart ETH gateway in different directions to ensure that it is reliably installed.
----End
15.6 (Optional) Installing Temperature Sensors
Preparations
Materials: temperature sensors, cable ties
Context
Temperature sensors should be installed inside IT cabinets and network cabinet.
The number of temperature sensors to be installed inside each cabinet depends on the
customer requirement. This section describes how to install six temperature sensors inside
each cabinet.