FusionModule2000 Smart Modular Data Center
Installation Guide
10 Installing the Aisle Containment
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
135
Figure 10-45
Door panel tilting down
3.
If door panels mismatch, loosen screws between the posts and cabinets and insert
washers to make the door panels on the same plane when they are closed, as shown by (3)
in
. After adjustment, tighten all screws.
4.
Tighten the screws connecting the door posts and the skylight connective plates.
Step 5
Place a door box.
Two types of door boxes are available: 1100 mm long and 1200 mm long. Door boxes are packed
with revolving doors.
When installing the door boxes, pay attention to the left, right, and length labels on the door boxes.
The two types of door boxes can be installed in a similar way. The following installation procedure
uses the 1200 mm long door box as an example.
1.
Put a door box hanging kit on the cabinet, and insert the tongue of the door box fastener
into the gap between the cabinet frame and the top panel, as shown in
2.
Mount the door box on the door box hanging kit, push the door box rightwards until it
touches the door post, and insert the two tongues on the right side into the stop holes on
the door post, as shown by (1) in
3.
Secure the door box to the door box hanging kit using three M5 screws, as shown by (2)
in
4.
After confirming that the door box is level, partially secure the door box to the cabinet,
as shown by (2) in