l
If the value of a counter is always displayed as (indicates the value zero), you can
infer that the services related to this counter are faulty. Rectify the fault.
----End
4.6.5 Restarting/Deleting MBTS Commissioning Tasks
This section describes how to restart or delete ongoing MBTS commissioning tasks.
Prerequisite
Certain MBTS commissioning tasks are created.
Procedure
Step 1
Choose
Configuration
>
Auto Deployment
>
MBTS Auto Deployment
. The
MBTS Auto
Deployment
window is displayed.
Step 2
Restart or delete MBTS commissioning tasks as required.
Option
Description
Restarting MBTS
commissioning tasks
Select one or multiple MBTSs from
MBTS List
, and then click
on the toolbar to restart the selected MBTS commissioning
tasks.
Deleting MBTS
commissioning tasks
Select one or multiple MBTSs from
MBTS List
, and then click
on the toolbar to delete the selected MBTS commissioning tasks.
----End
4.7 Confirming the Completion of MBTS Commissioning
This chapter describes how to confirm an MBTS commissioning task. After the service
verification of an MBTS is complete, the MBTS commissioning task changes to the status for
confirmation. You need to manually confirm the completion of the MBTS commissioning.
Prerequisite
The MBTS service verification is complete.
Context
l
If some alarms are still not cleared during the commissioning, it is recommended that you
do not confirm the completion of the commissioning task, so that you can view and handle
these alarms easily.
l
After you confirm that the commissioning task is complete, the alarms related to all the
GBTS and NodeB commissioning procedures cannot be viewed any longer.
4 Commissioning the MBTS in GU Mode on the M2000
3900 Series Multi-Mode Base Station
Commissioning Guide
4-22