Once the valve is re-powered, certain premix fuel/air configuration elements, which are specific to a valve + FARMOD are
automatically copied from the FARMOD into the new electronics. These include the Base Curve, Correction Curve, motor
full stroke and Pre Ign. Air Level.
4.
Navigate to the Valve Production Cloning menu. Upload the saved valve configuration to the new electronics, following the
Configured Valve Procedure
in
CHAPTER 7
, cloning all parameters
EXCEPT THE BASE CURVE (if valve is a premix / V2V
model)
. Refer to
Fig. 138
and the
Configured Valve Procedure
in
CHAPTER 7
for detailed cloning steps.
a. If all of the items shown in
Fig. 138
are checked, the following items are cloned; Valve name + Modbus a baud
rate, Valve General Settings, Units, Access Levels Settings, Valve Security Settings, Proof of Closure setup, Pressure
Module Lockout Types and VPS Setup, Fuel/Air OEM Setup + Ignition Setup.
b. Note that the user will need to re-commission the Pressure Module Hi-Gas and Lo-Gas limit settings by running the
burner.
Fig. 138: Valve Production cloning configuration groups selection.
5.
If a Pressure Module is used, navigate to the PRESSMOD tab by selecting the following: Attached valve -> Setup & Tests ->
Settings -> PRESSMOD. Refer to
Fig. 139
.
a. Accept the Pressure Module (PRESSMOD).
Fig. 139: Pressure Module Tab.
6.
Select the POC tab.
a. Accept the Proof of Closure Switch(es) (POCs) configuration. Refer to