3.5.3.
3.5.3. Rack-Mounting (Style-5054)
Rack-Mounting (Style-5054)
ATevo can be installed into most 23in/584mm and 24in/610mm relay racks with standard EIA
hole spacing. ATevo’s enclosure does not need to be modified for rack mounting, but a special
kit is required. The kit includes two (2) mounting brackets, appropriate hardware, and
Installation Instructions for the rack-mounting procedure.
When rack-mounting ATevo, consider the following:
1. Rack must be strong enough to properly support the unit’s weight. Refer to the Weight
Table in
2. Select conduit entrances such that planned ac input and dc output conduit is accessible
after rack-mounting. Note the standard pre-fab conduit knockouts located on the sides,
top, and bottom of the enclosures.
3. Location requirements:
a. Free of drips and splatter. If falling particles and liquids are a problem, install a
NEMA Type-2 drip shield accessory.