Test Screens
Test Screens
The remaining screens are test screens. They prompt the user through an interactive
process to verify ATevo’s operation. The process will:
• Require the user to confirm that LED indicators are lit, that relays change state, and
that the set points are correct.
• Simulate alarm conditions and prompt the user to verify the alarms operate and are
confirmed by any connected SCADA devices.
• Explain how to verify ATevo calibration and automatically enter calibration mode if
required.
After the Hindle Health System completes testing, ATevo will return to the Home Screen. An
event will be added to the log file along with a time and date stamp. The results of each
test are included in the log file. The result status will indicate that each test PASSED,
FAILED, or was NOT RUN. The resulting log file can be used to prove NERC compliance
requirements for things such as verifying correct float voltage.
Last modified: 11 March 2021
HindlePower Inc
ATevo Operations–Single Phase Input–Group II (30-100 Adc Output) - 1_en
Copyright HindlePower Inc. 2021
Page 108 of 171