GMV5 DC INVERTER VRF UNITS SERVICE MANUAL
100
Part 3 Commissioning Process
Note:
! It is forbidden to directly connect the compressor with power supply and forcibly power it on
during commissioning and maintenance.
! Engineering commissioning operations must be performed on the GMV5 serial unit. Otherwise,
the unit cannot properly run.
! Before commissioning is completed, the main board of ODU displays "module address 0F A0"
and that of IDU
displays “A0”.
! A module must be set to master module and only one can be set during commissioning.
! An IDU must be set to master IDU and only one can be set during commissioning.
! Other functions can use the factory settings if there are not special engineering requirements.
I. Necessity of VRF Engineering
Commissioning
Different form ordinary air conditioning units, the VRF system raises high design requirements and easily
incurs operation-affected factors such as impurities and water during engineering installation. Due to the
requirements on engineering design/installation complexity and high-precise system control,
commissioning is mandatory after engineering installation. Only a qualified unit can be delivered for use.
II. Required Files and Tools for Engineering
Commissioning
1. Required Tools for Engineering Commissioning of GREE VRF
Inner hexagon spanner
Digital thermometer
Shifting spanner
Noise meter
Cross screwdriver
Clamp meter
Straight screwdriver
Digital multimeter
Vacuum pump
Electricity meter
Electronic balance
Timer
System high and low pressure gauges
for corresponding refrigerants
Step ladder
Wind-speed transmitter
The GMV5 VRF provides two commissioning methods. One is to perform commissioning by pressing
buttons on the main board of ODU. The other is to perform commissioning on a PC through professional
software. Parameters of the ODU and IDU can be simultaneously displayed with the second method.
(For details about these methods, refer to respective instructions.)
2. Commissioning Files
The following commissioning files are required to record installation and commissioning of units:
pre-commissioning scheme determination meeting minutes, commissioning personnel record tables,
commissioning system appearance check record tables, commissioning data record tables, and
commissioning reports. See attached tables for file formats.
III. Engineering Commissioning Procedures
Step 1: Pre-commissioning Preparations
1.1 Overall Commissioning Plan
Before commissioning, the person-in-charge should learn about the overall engineering progress plan,
overall workload of engineering commissioning, possible influence factors in achieving the
commissioning progress, and required labors and materials.
1.2 Composition of Commissioning Members
Commissioning members comprise aftersales commissioning personnel and installation personnel.
All commissioning participants must take part in professional training courses before unit commissioning.
All participants can be grouped as required and each group should include at least professional
Содержание GMV-224WM/B-X
Страница 1: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL T1 R410A 50 60Hz GC201508...
Страница 6: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 3 2 Piping Diagram of GMV 400WM B X and GMV 450WM B X...
Страница 27: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 24...
Страница 29: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 26 V Construction Organization Process...
Страница 38: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 35...
Страница 45: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 42 Part 5 Piping Connection Schematic Diagram of Piping Connection...
Страница 47: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 44 GMV 504WM B X GMV 560WM B X and GMV 615WM B X...
Страница 156: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 153 low press ure air pipe...
Страница 158: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 155 2 Low exhaust temperature protection E2...
Страница 159: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 156 3 System high pressure protection E1 4 System low pressure protection E3...
Страница 160: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 157...
Страница 161: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 158 5 System refrigerant lacking protection U4...
Страница 162: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 159 6 System high pressure ratio protection J8...
Страница 163: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 160 7 System low pressure ratio protection J9...
Страница 165: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 162 11 Pressure sensor fault...
Страница 224: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 221 2 Model GMV 335WM B X Exploded View...
Страница 227: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 224 3 Model GMV 400WM B X GMV 450WM B X Exploded View...
Страница 230: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 227 4 Model GMV 504WM B X GMV 560WM B X GMV 615WM B X Exploded View...
Страница 242: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 239...
Страница 248: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 245 Click Finish...
Страница 250: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 247 Check I accept the terms in the License Agreement and click Next...
Страница 254: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 251 Click Next Installing...
Страница 255: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 252 Click Close...
Страница 272: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 269...
Страница 277: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 274 Power input Gateway Running Alarm Power Address Function...
Страница 287: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 284 1 4 2 5 Communication Debug...
Страница 297: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 294...
Страница 300: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 297 11 In the displayed window select I Agree and click Next to continue...
Страница 304: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 301...
Страница 307: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 304...
Страница 315: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 312 After detection detected devices will be listed in the Net tree...
Страница 349: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 346...
Страница 352: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 349 11 In the displayed window select I Agree and click Next to continue...
Страница 375: ...GMV5 DC INVERTER VRF UNITS SERVICE MANUAL 372 JF00302751...