GREER COMPANY
Crane Systems
GREER COMPANY 1918 East Glenwood Place, Santa Ana, CA 92705 TEL: (714) 259-9702 FAX: (714) 259-7626
MicroGuard® RCI 510/400 CALIBRATION MANUAL PN W450189A 09/09/02
29 of 65
Cranes equipped with one winch can omit No. 5,
but still require a lifting point selection when 2 or
more lift point options exist.
Note
:
Any stowable
attachment (stowed or not stowed) that will be
selected for erection must first be selected as
‘stowed.’
CONFIGURATION SELECTION
Before proceeding with further calibrations, ensure that the crane configuration setup is correct
and that the calibration configuration selection is correct.
♦
The system automatically chooses the configuration last selected each time the system is
powered up.
♦
The system automatically records the configuration last selected when in the normal
operational mode.
♦
If changes have been made to the crane configuration, return to
the normal
operational mode
and reenter the crane configuration data applicable to the area of
change
before calibrating.
♦
When changes are made after the initial calibration,
only
the area(s) relating to the change
will require recalibration.
♦
When calibrating the main boom, always select “lifting over the main boom.”
All calibrations pertaining to the main boom require that the operator lift and measure from
the main boom.
♦
If there is a stowed attachment on the boom, select it on the display as “stowed.” If nothing
is stowed, select “nothing stowed.”
ACCESSING THE NORMAL OPERATIONAL MODE
Press A to Command 01 Run.
A system safety check will begin followed by a printed
warning message and a return to the
normal operational mode.
or
Press Exit
repeatedly until it no longer says “Exit” to access the
normal operational
mode.
CRANE SET UP CATEGORIES
Review the operator’s manual and the following categories before starting the crane setup
routine on page 31.
1)
Outriggers, tires, rigging/travel mode.
2)
Applicable to cranes with multiple boom mode selections: active tip, modes A & B, main
boom + manual, etc. If the crane has no boom options other than the main boom,
skip this step.
3)
Auxiliary head, fitted or not fitted.
4)
Erected attachments (see notes below).
5)
Lifting point for front winch.
6)
Lifting point for rear winch.