Cleaning and maintenance
8.4
Record on inspection and
maintenance
Perform maintenance at least once a year, or
when the inspection shows the state of
installation that requires maintenance.
The record on putting into operation, inspections and
maintenance serves as an attachment for copying.
The performed inspections should be verified by signature and
date.
Inspection and maintenance works according to need
Page
Date:
______
Date:
______
Date:
______
1.
Check the condition of installation
2.
Perform visual and functional inspection
4.
Establishing operating pressure
•
Examine the pre-pressure of expansion container
•
Operating pressure is set to
• Discharging air from the heating installation.
• Check of the safety valve for heating
5.
Clean the water filter
6.
Check for damages to electrical lines
7.
Check whether the electrical connectors for
operating the boiler and the used elements stand
firmly, and tighten them if necessary.
8.
Check the functions of the thermostatic regulator on the
boiler
9.
Check the function of safety parts
10.
Check the function of the remote control
11.
Check the insulation of the rod heaters
12.
Check the function of connector for grounding
13.
Check the isolation of the electrical switchboard
14.
Check the function of the pump for heating
15.
Make a final control of the inspection works and
document the results of the measurement and testing
16.
Confirmation of a professionally conducted inspection
Seal / Signature
Seal / Signature
Seal / Signature
Table:
Record on inspection and maintenance