Si12-411A
Outdoor Unit (50 / 52 / 58 / 68 / 75 Class)
Removal Procedure
243
2.2
Removal of
Electrical BOX
Procedure
Warning
Be sure to wait 10 minutes or more after turning off all power supplies
before disassembling work.
Step
Procedure
Points
1. Removing the tie wires
Remove the piping in the
backward direction.
1
The figure shows the tie
pipe connections.
2
Remove the terminal
board fitting screw.
Match the colours of the tie
wires to A, B, C and D ports
as follows.
(1) - Black Power
(2) - White Power
(3) - Red Transmission
Wires are fixed to the
terminal board with screws.
Terminal board is made of
integral moulded resin.
Содержание FTKE25BVM
Страница 1: ...C Series Applied Models zInverter Multi Cooling Only zInverter Multi Heat Pump Si12 411A...
Страница 6: ...Si12 411A Table of Contents v Index i Drawings Flow Charts v...
Страница 7: ...Si12 411A vi Table of Contents...
Страница 67: ...Specifications Si12 411A 56 Specifications...
Страница 81: ...Printed Circuit Board Connector Wiring Diagram Si12 411A 70 Printed Circuit Board Connector Wiring Diagram...
Страница 131: ...Instruction Si12 411A 120 System Configuration CDK X D 25 35 50 60 C Names of parts Indoor Unit 3 6 8 9 10 7 1 4 5 2...
Страница 173: ...Instruction Si12 411A 162 System Configuration...
Страница 227: ...Check Si12 411A 216 Service Diagnosis...
Страница 268: ...Si12 411A Others 257 Part 8 Others 1 Others 258 1 1 Test Run from the Remote Controller 258 1 2 Jumper Settings 259...
Страница 295: ...Si12 411A iv Index...
Страница 298: ...Si12 411A Printed in Singapore 03 2005 AK COS...