6.4.3
Install conductor rail system
Procedure for the installation:
It is sensible to start the installation at one end cap and install the conductor rail along the route.
Work steps:
→
Indicate the installation location for line feeds, customer-side fixed points, terminal boxes, expansion points, air gaps and the
course of the conductor rail on the installation structure according to the layout and allocation plan on the substructure.
→
Prepare the line feed and guide (if present).
→
Install the conductor rail (see Section 6.4.3.1).
→
Install conductor rail sections.
→
Check the mechanical installation.
Test steps to be performed during installation:
→
Check the design against the layout and allocation plan.
→
Maintain the hanger clamp distances; the rails must be audibly engaged in the hanger clamp.
→
All transfers and bends must be tested for functionality. Current collectors must not jam when passing through. Check for free
passage with a single current collector.
→
Cable routing (laying, marking, etc.) must be checked.
→
Check the horizontal and vertical deviation of the conductor rail system! The deviation from the ideal line may be max. ±5 mm.