Please refer to the project-specific documents for the exact position of the fixed points.
NOTE!
Before the conductor rails are connected to each other, the anchor clamps must first be slid
onto the conductor rails.
Anchor clamps are positioned to the right and left of a hanger clamp.
Required tools:
◼
Open-end wrench SW8
Work steps:
→
Slide the anchor clamps onto the clipped-in conductor rail section on the right and left (see Fig. 87). When sliding on the anchor
clamps, ensure that the two side screws on the anchor clamps point away from the hanger clamp.
→
Tighten the two side screws (Pos. 1) on the anchor clamp (see Fig. 86). Observe the tightening torque of 10 Nm. If present, the
adjusted air gap of the expansion points in the expansion unit must be checked again on the closest expansion units after the
fixed point has been tightened (see Section 6.4.3.7).
Fig. 86: Side screws on the anchor clamp
Fig. 87:
Slide anchor clamps 0813 onto the conductor rail