7.2.2
Initial commissioning of the conductor rail system
→
Conduct a complete run along the conductor rail (walking pace).
After initial commissioning, a further review must be conducted to detect any damage or problems in the system.
Visual inspection of the product/system after initial commissioning:
→
Current collector undamaged and without signs of heavy wear.
→
Conductor rail components undamaged and in the proper location. No displacements or distortions. Check hanger clamps, end
caps and fixed points in particular!
→
Check that there are no visible signs of heavy wear (chips, plastic parts, etc.). Signs of heavy wear indicate that installation
clearances and their tolerances are not being complied with. This can sometimes also be the case for individual sections of the
route.
NOTE!
The current collectors must not become caught, stick or scrape!
Where necessary, repair any faults and conduct settings work.