1-85
Cisco ONS 15454 DWDM Procedure Guide, R8.0
78-17704-02
Chapter 1 Install the Shelf and Common Control Cards
NTP- G16 Perform the Shelf Installation Acceptance Test
Switch(config-line)#
login
Switch(config-line)#
line vty 5 15
Switch(config-line)#
password yyyyyy
Switch(config-line)#
login
Switch(config-line)#
end
Stop. You have completed this procedure.
NTP-G16 Perform the Shelf Installation Acceptance Test
Step 1
If you installed an ONS 15454 ETSI shelf, complete
by verifying that each applicable
procedure was completed.
Purpose
Use this procedure to perform a shelf installation acceptance test for the
ONS 15454 ETSI or ONS 15454 ANSI.
Tools/Equipment
Voltmeter
Prerequisite Procedures
Applicable procedures in
Chapter 1, “Install the Shelf and Common
Required/As Needed
Required
Onsite/Remote
Onsite
Security Level
None
Table 1-12
ONS 15454 ETSI Shelf Installation Task Summary
Description
Completed
NTP-G1 Unpack and Inspect the Shelf Assembly, page 1-6
NTP-G2 Install the Shelf Assembly, page 1-8
NTP-G3 Open and Remove the Front Door, page 1-21
NTP-G4 Open and Remove the FMEC Cover (ETSI Only), page 1-25
NTP-G6 Install the MIC-A/P and MIC-T/C/P FMECs (ETSI Only), page 1-30
NTP-G7 Install the Power and Ground, page 1-32
NTP-G8 Install the Fan-Tray Assembly, page 1-42
NTP-G10 Attach Wires to Alarm, Timing, LAN, and Craft Pin Connections, page
1-49
NTP-G12 Install and Close the FMEC Cover (ETSI Only), page 1-64
NTP-G14 Install DWDM Equipment, page 1-67
NTP-G15 Install the Common Control Cards, page 1-75
NTP-G145 Connect a Multishelf Node and Subtending Shelves to an MS-ISC-100T
Card, page 1-81
NTP-G158 Connect a Multishelf Node and Subtending Shelves
NTP-G159 Configure a Cisco Catalyst 2950 for a Multishelf Node, page 1-83
(if you
completed
NTP-G158 Connect a Multishelf Node and Subtending Shelves to a
)