1-71
Cisco ONS 15454 DWDM Procedure Guide, R8.0
78-17704-02
Chapter 1 Install the Shelf and Common Control Cards
NTP- G351 Install the Y-Cable Module Tray
DLP-G351 Install the Y-Cable Module Tray
Step 1
The Y-cable module tray requires 2 RU in a standard 19-inch (482.6-mm) or 23-inch (584.2-mm) rack.
Locate the RMU space specified in your site plan. Refer to the “Shelf Assembly Hardware” chapter in
the
Cisco ONS 15454 DWDM Reference Manual
for common site configurations, and use the
Cisco MetroPlanner Internal Connections Report to determine how many Y-cable modules you need to
install.
Step 2
Verify that the mounting brackets attached to the unit are correct for your rack size. Complete
Reverse the Mounting Bracket to Fit a 19-inch (482.6-mm) Rack (ANSI Only)” task on page 1-10
required.
Step 3
Align the chassis with the rack mounting screw holes, insert the four screws, and tighten.
Step 4
Return to your originating procedure (NTP).
DLP-G30 Install the FlexLayer Shelf
Step 1
The FlexLayer shelf requires 1 RU in a standard 19-inch (482.6-mm) or 23-inch (584.2-mm) rack.
Locate the RMU space specified in your site plan. Refer to the “Shelf Assembly Hardware” chapter in
the
Cisco ONS 15454 DWDM Reference Manual
for typical DWDM site layout plans.
Step 2
A set of mounting brackets are included with the FlexLayer mounting kit, one set each for 19-inch
(482.6-mm) or 23-inch (584.2-mm) racks. Verify that your chassis is equipped with the correct set of
brackets for your rack. Change the brackets as required.
Purpose
This task installs the Y-cable tray. The Y-cable tray can store up to eight
Y-cable protection units.
Tools/Equipment
#2 Phillips Dynamometric screwdriver
Y-cable module tray(s) (15454-YCBL-LC)
Cisco MetroPlanner Internal Connections Report
Prerequisite Procedures
None
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
None
Purpose
This task installs the FlexLayer shelf. Perform this task if you are
installing any FlexLayer modules.
Tools/Equipment
#2 Phillips Dynamometric screwdriver
FlexLayer shelf assembly (15216-FL-SA)
#14 AWG wire (minimum) for frame grounding
Prerequisite Procedures
None
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
None