Cisco ONS 15454 DWDM Procedure Guide, R8.0
78-17704-02
Chapter 1 Install the Shelf and Common Control Cards
NTP- G7 Mount Multiple Shelf Assemblies in a Rack
installed above third-party equipment, you must provide a minimum spacing of one inch (25.4 mm)
between the third-party shelf assembly and the bottom of the ONS 15454. The third-party equipment
must not vent heat upward into the ONS 15454.
Step 1
Verify that the proper fuse and alarm panel has been installed in the top mounting space. If a fuse and
alarm panel is not present, you must install one according to manufacturer’s instructions:
•
The fuse rating for both ETSI and ANSI chassis must not exceed 30A.
Step 2
Mount the first shelf assembly in the bottom of the rack using the
“DLP-G5 Mount the Shelf Assembly
in a Rack (One Person)” task on page 1-13
or the
“DLP-G6 Mount the Shelf Assembly in a Rack (Two
.
shows a three-shelf ONS 15454 ETSI bay assembly.
Figure 1-4
Three-Shelf ONS 15454 ETSI (ONS 15454 SDH) Bay Assembly
Step 3
(ETSI only) Mount the air ramp above the ONS 15454 ETSI according to the
Ramp for Standard and Deep Door ONS 15454” task on page 1-18
The air ramp is needed if you install more than one ONS 15454 ETSI shelf in a rack. To ensure that the
air ramp is secure, use one or two M6 mounting screws for each side of the shelf assembly.
shows how to mount an air ramp in the rack.
61583
Fuse and Alarm Panel,
mountable in the rack
if the rack is 2200 mm
(86.6 in.) high or higher
Air Ramp
ETSIs (SDH)
Air Ramp