If the equipment room does not have one, you must build a main distribution frame (MDF) that
connects the media gateways to the building phone network and to the public switched
telephone network (PSTN). The tasks include the following:
●
Physical requirements and layout
on page 13
●
Main distribution frame hardware installation
on page 17
If the installation will use a patch panel rather than a main distribution frame, use the procedures
in
Chapter 3: Installing the patch panel
on page 29.
Physical requirements and layout
Before installing the MDF and other equipment in the equipment room, ensure that there is
adequate space and there is a plan for placing the equipment.
Installation space requirements
Make sure there is adequate space for the following pieces of equipment:
●
Sneak fuse panels and emergency transfer units
on page 13
●
110-type hardware
on page 13
●
Cable Slack Manager
on page 14
Sneak fuse panels and emergency transfer units
You need about 8 inches (20 centimeters) of horizontal wall space for each column of sneak
fuse panels. Horizontal wall space must also be provided for emergency transfer units.
110-type hardware
The trunk/auxiliary field and the distribution field are mounted on the same wall. Each 110P-type
terminal block is 8.5 inches (21.6 centimeters) wide. Vertical patch cord troughs are 5.31 inches
(13.4 centimeters) wide and horizontal patch cord troughs are 23 inches (58.4 centimeters)
wide.
Each 110A-type terminal block is 10.8 inches (27.4 centimeters) wide; however, no horizontal
patch cord troughs are used and the blocks are shorter than 110P-type terminal blocks. This
allows the 110A-type terminal blocks to be stacked. Therefore, the 110A-type hardware requires
less space than the 110P-type hardware on a per-station basis.
Содержание 03-300686
Страница 1: ...Installing and Connecting the MDF and Telephones 03 300686 Issue 3 Release 5 0 January 2008 ...
Страница 8: ...Contents 8 Installing and Connecting the MDF and Telephones ...
Страница 28: ...Installing the main distribution frame 28 Installing and Connecting the MDF and Telephones ...
Страница 32: ...Installing the patch panel 32 Installing and Connecting the MDF and Telephones ...
Страница 40: ...Media gateway connections to the MDF 40 Installing and Connecting the MDF and Telephones ...
Страница 53: ...Completing a provisioning plan Issue 3 January 2008 53 Figure 25 Port Assignment Record Form ...
Страница 108: ...Installing and wiring telephones and trunks 108 Installing and Connecting the MDF and Telephones ...
Страница 134: ...Installing and wiring telephone power supplies 134 Installing and Connecting the MDF and Telephones ...
Страница 156: ...156 Installing and Connecting the MDF and Telephones Index ...