5 - 18
Chapter Five
Figure 5-13
The Load/Control screen allows load to be pre-set and then Accepted (applied) or
Rejected (removed).
Operating the load/control screen
•
Use the Load Control source selector (on the Load/Supply screen) to select “LOCAL”
control.
•
Use the
+ and - keys to adjust the values for kVA, KW, and power factor.
•
When suitable values are shown tap the green Accept/Reject
I
key to apply the load.
•
Once the load is applied you can visit any of the other System Monitor screens that we
have described to monitor the progress of the test.
•
When testing is completed, return to this screen and tap the red Accept/Reject
O key
to remove the load.
In an emergency, press the load bank Emergency stop button to remove load immediately
and stop the fans. See “Emergency Shutdown Procedures” on page 3-11 for more details.
Note:
The System
Monitor’s load control
will not work if the load
bank communications
are active (see figure
5-7).
Содержание Froment 8800 Series
Страница 1: ...8800 SERIES High Voltage Load Banks User Manual Power Technologies ...
Страница 2: ......
Страница 10: ......
Страница 42: ...Load Bank Installation and Setup 2 14 ...
Страница 106: ...A 4 Appendices Figure A 5 8800 Transformer view ...
Страница 110: ...A 8 Appendices Transformer Maintenance Schedule ...